Double Shaft Shredder-NS-S1200 Development and Delivery Project

Client Country: Portugal
Project Timeline
February 2025 -November 2025
Project Plan

Phase 1: Requirements Research and Solution Design (February 2025 – March 2025)

Phase 2: Equipment Design and Manufacturing (May 2025 – July 2025)

Phase 3: Testing and Commissioning (4 July 2025 – 23 July 2025)

Phase 4: Equipment Shipping and Installation (24 July 2025 – 10 September 2025)

Phase 5: Operation and Acceptance (October 2025-November 2025)

PVC Flooring Crushing and Grinding Recycling Line

Client Country: Netherlands

Project Timeline

Project Start Date 03 April 2023

Expected Completion Date: 30 December 2023

Project Plan

Phase 1: Requirements Research and Solution Design (03 April 2023- 03 June 2023)

Phase 2: Equipment Design and Manufacturing (04 June 2023 – 04 September 2023)

Phase 3: Testing and Commissioning (05 September 2023 – 24 September 2023)

Phase 4: Equipment Shipping and Installation (25 September 2024 – 10 December 2023)

Phase 5: Operation and Acceptance (11 December 2023-30 December 2023)

Pipe Crushing and Grinding Recycling Line

Client Country: Spain

Project Timeline

Project Start Date August 2022

Expected Completion Date: May 2023

Project Plan

Phase 1: Requirements Research and Solution Design (August 2022- September 2022)

Phase 2: Equipment Design and Manufacturing (October 2022 – December 2022)

Phase 3: Testing and Commissioning (January 2023 – 20 January 2023)

Phase 4: Equipment Shipping and Installation (21 January 2023 – 26 April 2023)

Phase 5: Operation and Acceptance (27 April 2023-17 May 2022)

PVC Flooring Crushing and Grinding Recycling Line

Client Country: UK

Project Timeline

Project Start Date 04 November 2021

Expected Completion Date: 30 December 2023:

Project Plan

Phase 1: Requirements Research and Solution Design (04 November 2021-04 January 2022)

Phase 2: Equipment Design and Manufacturing (05 January 2022 – 05 April 2022)

Phase 3: Testing and Commissioning (06 April 2022 – 25 April 2022)

Phase 4: Equipment Shipping and Installation (26 April 2022 – 17 July 2022)

Phase 5: Operation and Acceptance (18 July 2022-06 August 2022)

PVC Plates Crushing and Grinding Recycling Project

Client Country:Belgium

Project Timeline

Project Start Date August 2023

Expected Completion Date: April 2024:

Project Plan

Phase 1: Requirements Research and Solution Design (August 2023- September 2023)

Phase 2: Equipment Design and Manufacturing (October 2023 – December 2022)

Phase 3: Testing and Commissioning (1 January 2024 – 20 January 2024)

Phase 4: Equipment Shipping and Installation (21 January 2024 – 5 April 2024)

Phase 5: Operation and Acceptance (6 April 2024-25 April 2024)

PVC Sheets Crushing and Grinding Recycling Project

Client Country: Spain

Project Timeline

Project Start Date: October 2023

Expected Completion Date: 26 June 2024

Main Equipment List

  1. Crusher:NSGB-1300

Crushing Capacity: 1.5t-2t per hour  

  Power:90KW  

  1. Rotary Miller: SMF-600  
  2. Belt Conveyor :SSJ-1200
  3. Pulse Dust Collector

This project aims to assist the client in efficiently recycling and reusing plastic waste through advanced PVC sheet crushing and grinding technology, reducing production costs and environmental pollution.

SPC Flooring Crushing and Grinding Recycling Project in the USA

Client Country: USA

Project Timeline

Project Start Date: 21 March 2024

Estimated Completion Date: December 2024

Main Equipment List:

Crusher (NSP-850 Horizontal Crusher)

-Capacity: 400-800kg per hour  

-Power: 55kw 

Disk Mille (MF-600)

   – Disk Miller: 120-300 kg per hour  

Automatic Feeding Conveyor System

Pulse Dust Collector System

Current Progress

At present, the installation and debugging of the equipment have been completed. Product optimization and shipping are expected to be completed by mid-November.

Vertical Plastic Crusher-NSGB-1000

Project Title: 《Vertical Plastic Crusher NSGB-1000 Development and Delivery Project》

Client Country: Germany

Project Duration: January 2024 -September 2024

Project Plan:

Phase 1: Requirements Research and Solution Design (January 2024 – February 2024)

Phase 2: Equipment Design and Manufacturing (March 2024 – May 2024)

Phase 3: Testing and Commissioning (1 June 2024 – 20 June 2024)

Phase 4: Equipment Shipping and Installation (21 June 2024 – 5 September 2024)

Phase 5: Operation and Acceptance (6 September 2024-25 September 2024)